Layout and marking for earthwork in excavation for foundation. মাটি কাটার জন্য লেআউট করা।
Layout and marking for earthwork in excavation for foundation. মাটি কাটার জন্য লেআউট করা।
Materials for
2
sft
| Material | Qty | Unit | Unit Price | Amount |
|---|---|---|---|---|
| Head Masson (Civil) | 1 | person | 800.00 | 800.00 |
| Skill Labour (civil) | 101 | person | 550.00 | 55,550.00 |
| Ordinary Labour | 302 | person | 550.00 | 166,100.00 |
| Miscellaneous (taka) | 40800 | LS | 1.00 | 40,800.00 |
| ballah | 2000 | rft | 60.00 | 120,000.00 |
| Cement | 38.8 | bag | 575.00 | 22,310.00 |
| Sand 1.2 FM | 245 | cft | 45.00 | 11,025.00 |
| Bricks | 10000 | Nos | 13.00 | 130,000.00 |
| Grand Total | 546,585.00 | |||