Brick work with first class bricks in superstructure (1:6)
Brick work with first class bricks in superstructure (1:6)
Materials for
1
cft
| Material | Qty | Unit | Unit Price | Amount |
|---|---|---|---|---|
| Scaffolding | 25 | sft | 30.00 | 750.00 |
| Ordinary Labour | 2.25 | person | 550.00 | 1,237.50 |
| Bricks | 1100 | Nos | 13.00 | 14,300.00 |
| Sand 1.2 FM | 36 | cft | 45.00 | 1,620.00 |
| Cement | 4 | bag | 575.00 | 2,300.00 |
| Head Masson (Civil) | 0.1 | person | 800.00 | 80.00 |
| Skill Masson (Civil) | 1 | person | 750.00 | 750.00 |
| Skill Labour (civil) | 2.5 | person | 550.00 | 1,375.00 |
| Grand Total | 22,412.50 | |||