Brick work with first class bricks in superstructure (1:6)

Brick work with first class bricks in superstructure (1:6)
100.0000 cft
Materials for 1 cft
Material Qty Unit Unit Price Amount
Scaffolding 25 sft 30.00 750.00
Ordinary Labour 2.25 person 550.00 1,237.50
Bricks 1100 Nos 13.00 14,300.00
Sand 1.2 FM 36 cft 45.00 1,620.00
Cement 4 bag 575.00 2,300.00
Head Masson (Civil) 0.1 person 800.00 80.00
Skill Masson (Civil) 1 person 750.00 750.00
Skill Labour (civil) 2.5 person 550.00 1,375.00
Grand Total 22,412.50