125 mm brick work with first class bricks (1:4) in superstructure
125 mm brick work with first class bricks (1:4) in superstructure
Materials for
1
sft
| Material | Qty | Unit | Unit Price | Amount |
|---|---|---|---|---|
| Bricks | 480 | Nos | 13.00 | 6,240.00 |
| Sand 1.2 FM | 17 | cft | 45.00 | 765.00 |
| Cement | 2.6 | bag | 575.00 | 1,495.00 |
| Masson (Civil) | 0.75 | person | 700.00 | 525.00 |
| Skill Masson (Civil) | 0.1 | person | 750.00 | 75.00 |
| Skill Labour (civil) | 0.5 | person | 550.00 | 275.00 |
| Ordinary Labour | 3 | person | 550.00 | 1,650.00 |
| Scaffolding | 25 | sft | 30.00 | 750.00 |
| Grand Total | 11,775.00 | |||