Profit Overhead | Sub - Total 10.00% 3.50% | = = = | Tk. | 10,919.66 1,091.97 382.19 |
Total | = | Tk. | 12,393.82 | |
Add VAT with adjustment factor 1.06383 | 6.00% | = | Tk. | 791.10 |
| Grand Total | = | Tk. | 13,184.92 |
(i) Ground floor | Rate per sft | = | Tk. | 131.85 |
| Rate per sqm | = | Tk. | 1,419.23 |
Say, Tk. 1,419 .00 per sqm |
|
|
| |
|
|
|
|
|
Item No.- 05.4.1 |
|
|
|
|
12 mm thick (finished) silver grey situ mosaic in floor with Indian chips and with glass strip in/c 25 mm thick patent stone with BRICK-CHIPS: (white cement : grey cement = 1:1) |
|
|
|
|
Considering 100 sft of work |
|
|
|
|
A. Materials: |
|
|
|
|
| per kg | = | Tk. | 1,820.00 |
| per bag | = | Tk. | 553.00 |
| per kg | = | Tk. | 2,520.00 |
| each | = | Tk. | 140.00 |
| per rft | = | Tk. | 1,200.00 |
finish and 1/4 No. mason. 100 sft @ Tk. 2,543.41 | per % sft | = | Tk. | 2,543.41 |
B. Labour: |
|
|
|
|
Same as item No.- 05.1.1 100 sft @ Tk. 4,232.50 | per % sft | = | Tk. | 4,232.50 |
| Sub - Total | = | Tk. | 13,008.91 |
Profit | 10.00% | = | Tk. | 1,300.89 |
Overhead | 3.50% | = | Tk. | 455.31 |
| Total | = | Tk. | 14,765.11 |
Add VAT with adjustment factor 1.06383 | 6.00% | = | Tk. | 942.45 |
| Grand Total | = | Tk. | 15,707.56 |
(i) Ground floor | Rate per sft | = | Tk. | 157.08 |
| Rate per sqm | = | Tk. | 1,690.81 |
Say, Tk. 1,691 .00 per sqm |
|
|
| |
|
|
|
|
|
Item No.- 05.4.2 |
|
|
|
|
12 mm thick (finished) silver grey situ mosaic in floor with Pakistani chips and with glass strip in/c 25 mm thick patent stone with BRICK-CHIPS: (white cement : grey cement = 1:1) |
|
|
|
|
Considering 100 sft of work |
|
|
|
|
A. Materials: |
|
|
|
|
| per kg | = | Tk. | 1,820.00 |
| per bag | = | Tk. | 553.00 |
| per kg | = | Tk. | 2,800.00 |
| each | = | Tk. | 140.00 |
| per rft | = | Tk. | 1,200.00 |
finish and 1/4 No. mason. 100 sft @ Tk. 2,543.41 | per % sft | = | Tk. | 2,543.41 |
B. Labour: |
|
|
|
|
Same as item No.- 05.1.1 100 sft @ Tk. 4,232.50 | per % sft | = | Tk. | 4,232.50 |
| Sub - Total | = | Tk. | 13,288.91 |
Profit | 10.00% | = | Tk. | 1,328.89 |
Overhead | 3.50% | = | Tk. | 465.11 |
| Total | = | Tk. | 15,082.91 |
Add VAT with adjustment factor 1.06383 | 6.00% | = | Tk. | 962.74 |
| Grand Total | = | Tk. | 16,045.65 |
(i) Ground floor | Rate per sft | = | Tk. | 160.46 |
| Rate per sqm | = | Tk. | 1,727.19 |
Say, Tk. 1,727 .00 per sqm |
|
|
| |