|
|
|
| Profit | 10.00% 3.50% | = = | Tk. Tk. | 1,330.09 465.53 |
Total | = | Tk. | 15,096.53 | |||||
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 963.61 | ||
|
|
|
|
| Grand Total | = | Tk. | 16,060.14 |
(i) Ground floor |
|
|
|
| Rate per sft | = | Tk. | 160.60 |
|
|
|
|
| Rate per sqm | = | Tk. | 1,728.70 |
|
| Say, | Tk. | 1,729 .00 per sqm |
|
|
| |
|
|
|
|
|
|
|
|
|
Item No.- 05.9.1 |
|
|
|
|
|
|
|
|
10 mm thick (finished) coloured mosaic on wall with Indian chips |
|
|
|
|
|
|
|
|
Considering 100 sft of work |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Same as item No. 5.5.1 100 | sft | @ | Tk. | 13,265.00 | per % sft | = | Tk. | 13,265.00 |
| Ibs | @ | Tk. | 70.00 | per Ib | = | Tk. | 560.00 |
|
|
|
|
| Sub - Total | = | Tk. | 13,825.00 |
|
|
|
| Profit | 10.00% | = | Tk. | 1,382.50 |
|
|
|
| Overhead | 3.50% | = | Tk. | 483.88 |
|
|
|
|
| Total | = | Tk. | 15,691.38 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 1,001.58 | ||
|
|
|
|
| Grand Total | = | Tk. | 16,692.96 |
(i) Ground floor |
|
|
|
| Rate per sft | = | Tk. | 166.93 |
|
|
|
|
| Rate per sqm | = | Tk. | 1,796.83 |
|
| Say, | Tk. | 1,797 .00 per sqm |
|
|
| |
|
|
|
|
|
|
|
|
|
Item No.- 05.9.2 |
|
|
|
|
|
|
|
|
10mm thick (finished) coloured mosaic on wall with Pakistani chips |
|
|
|
|
|
|
|
|
Considering 100 sft of work |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Same as item No. 5.5.2 100 | sft | @ | Tk. | 13,515.00 | per % sft | = | Tk. | 13,515.00 |
| Ibs | @ | Tk. | 70.00 | per Ib | = | Tk. | 560.00 |
|
|
|
|
| Sub - Total | = | Tk. | 14,075.00 |
|
|
|
| Profit | 10.00% | = | Tk. | 1,407.50 |
|
|
|
| Overhead | 3.50% | = | Tk. | 492.63 |
|
|
|
|
| Total | = | Tk. | 15,975.13 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 1,019.69 | ||
|
|
|
|
| Grand Total | = | Tk. | 16,994.82 |
(i) Ground floor |
|
|
|
| Rate per sft | = | Tk. | 169.95 |
|
|
|
|
| Rate per sqm | = | Tk. | 1,829.34 |
|
| Say, | Tk. | 1,829 .00 per sqm |
|
|
| |
|
|
|
|
|
|
|
|
|
Item No.- 05.10.1 |
|
|
|
|
|
|
|
|
200 x 200 x 20 mm (finished) mosaic terrazo tiles flooring with Indian chips |
|
|
|
|
|
|
| |
Considering 100 sft of work (a) Cost of materials a) Sand-cement mortar base (3:1): |
|
|
|
|
|
|
| |
| bags | @ | Tk. | 395.00 | per bag | = | Tk. | 1,678.75 |
| cft | @ | Tk. | 1,400.00 | per % cft | = | Tk. | 98.00 |
b) Bottom of the tiles: sand - cement (2:1): | cft | @ | Tk. | 4,500.00 | per % cft | = | Tk. | 315.00 |
| bags | @ | Tk. | 395.00 | per bag | = | Tk. | 525.35 |
| cft | @ | Tk. | 1,400.00 | per % cft | = | Tk. | 23.38 |
c) Top of the tiles: | cft | @ | Tk. | 4,500.00 | per % cft | = | Tk. | 75.15 |
| kg | @ | Tk. | 26.00 | per kg | = | Tk. | 2,925.00 |
| bags | @ | Tk. | 395.00 | per bag | = | Tk. | 98.75 |
| kg | @ | Tk. | 18.00 | per kg | = | Tk. | 2,250.00 |
|
|
|
|
| Sub-total (a) | = | Tk. | 7,989.38 |