D. Cost of bed preparation: Area of bed: 1 x 45'-0" x 13'-2"= 592.65 | sft |
|
|
|
|
neat cement finishing 592.65 | sft @ Tk. sft @ Tk. | 0.32 per sft 21.58 per sft | = = | Tk. Tk. | 189.65 12,789.39 |
|
| Total for 305.56 cft | = | Tk. | 12,979.04 |
|
| Cost for 100 cft of work | = | Tk. | 4,247.62 |
|
| Using 8 times | = | Tk. | 530.95 |
E. Polythene as separator between pile layers during casting concrete 592.65 | sft @ Tk. | 319.44 per % sft | = | Tk. | 1,893.16 |
|
| Cost for 100 cft of work | = | Tk. | 430.26 |
Abstract of cosr for 100 cft of work |
|
|
| ||
|
|
| = | Tk. | 28,198.75 |
|
|
| = | Tk. | 1,199.80 |
|
|
| = | Tk. | 4,702.57 |
|
|
| = | Tk. | 530.95 |
|
|
| = | Tk. | 430.26 |
|
| Sub - Total | = | Tk. | 35,062.33 |
|
| Profit 10.00% | = | Tk. | 3,506.23 |
|
| Overhead 3.50% | = | Tk. | 1,227.18 |
|
| Total | = | Tk. | 39,795.74 |
Add VAT with adjustment factor | 1.06383 6.00% | = | Tk. | 2,540.15 | |
|
| Grand Total | = | Tk. | 42,335.89 |
|
| Rate per cft | = | Tk. | 423.36 |
|
| Rate per rft | = | Tk. | 294.00 |
|
| Rate per rm | = | Tk. | 964.61 |
| Say, Tk. | 965 .00 per meter |
|
|
|
|
|
|
|
|
|
Item No.- 09.10.2 |
|
|
|
|
|
12" x 12" Pre-cast pile with reinforced cement concrete (1 : 1.25 : 2.5) with stone chips. |
|
|
|
| |
Considering 40 rft long 12" x 12" size pile |
|
|
|
| |
Also Considering 100 rft pile making work using 100 cft concrete |
|
|
|
| |
|
|
| = | Tk. | 28,198.75 |
|
|
| = | Tk. | 1,199.80 |
|
|
|
|
|
|
Volume of concrete: |
|
|
|
|
|
11 x 12" x 12" x 40'-0" = 440 cft (a) Cost of shuttering: |
|
|
|
|
|
|
|
|
|
|
|
Sides: 1 x 12 x 40'-0" x 1'-0"= 480.00 Add wastage 5%= 24.00 | sft sft |
|
|
|
|
= 504.00 | sft | ||||
@ 3.05 Ib per sft= 1537.20
| Ibs @ Tk. | 27.44 per Ib | = | Tk. | 42,180.77 |
Sides: 2 x 12 x 40'-0"= 960.00 Vertical: 12 x 41 x 1'-0"= 492.00 | rft rft |
|
|
|
|
= 1452.00 Add wastage 5%= 72.60 | rft rft | ||||
1524.60 | rft | ||||
@ 1.79 Ib per rft = 2729.03
Stiffner: 6 x 20 x 1'-2" = 140.00 Clamps: 6 x 12 x 6"= 36.00 | Ibs @ Tk. rft rft | 24.94 per Ib | = | Tk. | 68,062.01 |
= 176.00 Add 5% wastage= 8.8 | rft rft | ||||
= 184.80 | rft | ||||
@ 0.956 Ibs per rft= 176.67 | Ibs @ Tk. | 24.94 per Ib | = | Tk. | 4,406.15 |
| kg @ Tk. | 160.00 per kg | = | Tk. | 3,200.00 |