4 x 4'-0"= 16 2 x 3'-0"= 6 |
|
|
|
|
= 22 rft @ | Tk. 25.00 per rft | = | Tk. | 550.00 |
4. 1" x 1" square pipe 4 rft @ | Tk. 38.00 per rft |
| Tk. | 152.00 |
|
| = | Tk. | 3,410.00 |
| Cutting wastage 3% | = | Tk. | 102.30 |
| Total (A) | = | Tk. | 3,512.30 |
(B) Cost of accessories: |
|
|
|
|
| Tk. 700.00 per set | = | Tk. | 2,800.00 |
| Tk. 260.00 each | = | Tk. | 520.00 |
| LS | = | Tk. | 585.88 |
| Total (B) | = | Tk. | 3,905.88 |
(C) Labour charge for fabrication, assembling and fitting-fixing in position |
|
|
|
|
| Tk. 1,000.00 each | = | Tk. | 1,500.00 |
| Tk. 600.00 each | = | Tk. | 900.00 |
| LS | = | Tk. | 320.00 |
| Sub total (C) | = | Tk. | 2,720.00 |
| Total (A+B+C) | = |
| 10,138.18 |
| Profit 10.00% | = | Tk. | 1,013.82 |
| Overhead 3.50% | = | Tk. | 354.84 |
| Total | = | Tk. | 11,506.84 |
Add VAT with adjustment factor | 1.06383 6.00% | = | Tk. | 734.48 |
| Grand Total | = | Tk. | 12,241.32 |
| Rate per sft | = | Tk. | 1,020.11 |
| Rate per sqm | = | Tk. | 10,980.46 |
Say, | Tk. 10,980 .00 per sqm |
|
|
|
|
|
|
|
|
Item No.- 14.9.3 |
|
|
|
|
Supplying, fitting and fixing aluminium top hung/casement window (silver colour) |
|
|
|
|
Considering 1 No. window |
|
|
|
|
Considering 3'-0" x 4'-0" = 12 sft of work |
|
|
|
|
(A) Cost of aluminium sections: |
|
|
|
|
|
|
|
|
|
2 x 4'-0"= 8 rft |
|
|
|
|
2 x 3'-0"= 6 rft |
|
|
|
|
= 14 rft @ | Tk. 50.00 per rft | = | Tk. | 700.00 |
4 x 4'-0"= 16 rft 2 x 3'-0"= 6 rft | Tk. 88.00 per rft | = | Tk. | 1,936.00 |
= 22 rft @ | ||||
4 x 4'-0"= 16 2 x 3'-0"= 6 | Tk. 24.00 per rft | = | Tk. | 528.00 |
= 22 rft @ | ||||
| Tk. 37.00 per rft |
| Tk. | 148.00 |
|
| = | Tk. | 3,312.00 |
| Add cutting wastage 3% | = | Tk. | 99.36 |
| Total (A) | = | Tk. | 3,411.36 |
(B) Cost of accessories: |
|
|
|
|
| Tk. 700.00 per set | = | Tk. | 2,800.00 |
| Tk. 260.00 each | = | Tk. | 520.00 |
| LS | = | Tk. | 585.88 |
| Total (B) | = | Tk. | 3,905.88 |
(C) Labour charge for fabrication, assembling and fitting-fixing in position |
|
|
|
|
| Tk. 1,000.00 each | = | Tk. | 1,500.00 |
| Tk. 600.00 each | = | Tk. | 900.00 |
| LS | = | Tk. | 320.00 |
| Sub total (C) | = | Tk. | 2,720.00 |