Item No.- 15.7 |
|
|
|
|
|
|
|
|
|
Flush pointing with cement mortar (1:2) to walls Considering 100 sft of work |
|
|
|
|
|
|
|
|
|
(a) Sand (F.M. 1.2) | 1.0 | cft | @ | Tk. | 1,400.00 | per % cft | = | Tk. | 14.00 |
(b) Cement (c) Labour
| 0.4 0.25 | bag | @ @ | Tk. Tk. | 395.00 600.00 | per bag | = = | Tk. Tk. | 158.00 150.00 |
| 0.5 | no | @ | Tk. | 500.00 | per day | = | Tk. | 250.00 |
| 1 | no | @ | Tk. | 320.00 | per day | = | Tk. | 320.00 |
(d) Washing of sand, scaffolding, curing, sundries, local carriage etc. |
|
|
| LS | = | Tk. | 192.00 | ||
|
|
|
|
|
| Sub - Total | = | Tk. | 1,084.00 |
|
|
|
|
| Profit | 10.00% | = | Tk. | 108.40 |
|
|
|
|
| Overhead | 3.50% | = | Tk. | 37.94 |
|
|
|
|
|
| Total | = | Tk. | 1,230.34 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 78.53 | |||
|
|
|
|
|
| Grand Total | = | Tk. | 1,308.87 |
|
|
|
|
|
| Rate per sft | = | Tk. | 13.09 |
|
|
|
|
|
| Rate per sqm | = | Tk. | 140.90 |
(i) For ground floor |
|
| Say, | Tk. | 141 .00 per sqm |
|
|
| |
|
|
|
|
|
|
|
|
|
|
Item No.- 15.8 |
|
|
|
|
|
|
|
|
|
Ruled pointing with cement mortar (1:2) to walls |
|
|
|
|
|
|
|
|
|
Considering 100 sft of work (a) Sand (F.M. 1.2) | 1.5 | cft | @ | Tk. | 1,400.00 | Per % cft | = | Tk. | 21.00 |
(b) Cement (c) Labour (i) Head mason | 0.5 0.25 | bag | @ @ | Tk. Tk. | 395.00 600.00 | per bag | = = | Tk. Tk. | 197.50 150.00 |
(ii) Mason | 1 | no | @ | Tk. | 500.00 | per day | = | Tk. | 500.00 |
(iii) Ordinary labour | 1 | no | @ | Tk. | 320.00 | per day | = | Tk. | 320.00 |
(d) Washing of sand, scaffolding, curing, sundries, local carriage etc. |
|
|
| LS | = | Tk. | 192.00 | ||
|
|
|
|
|
| Sub - Total | = | Tk. | 1,380.50 |
|
|
|
|
| Profit | 10.00% | = | Tk. | 138.05 |
|
|
|
|
| Overhead | 3.50% | = | Tk. | 48.32 |
|
|
|
|
|
| Total | = | Tk. | 1,566.87 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 100.01 | |||
|
|
|
|
|
| Grand Total | = | Tk. | 1,666.88 |
|
|
|
|
|
| Rate per sft | = | Tk. | 16.67 |
|
|
|
|
|
| Rate per sqm | = | Tk. | 179.44 |
(i) For ground floor |
|
| Say, | Tk. | 179 .00 per sqm |
|
|
| |
|
|
|
|
|
|
|
|
|
|
Item No.- 15.9 |
|
|
|
|
|
|
|
|
|
Raised / Tack pointing with cement mortar (1:2) to walls |
|
|
|
|
|
|
|
|
|
Considering 100 sft of work (a) Sand (F.M. 1.2) | 3 | cft | @ | Tk. | 1,400.00 | per % cft | = | Tk. | 42.00 |
(b) Cement | 1 | bag | @ | Tk. | 395.00 | per bag | = | Tk. | 395.00 |
(c) Cost of pumic stone (d) Labour
| 0.25 0.5 | no | @ @ | Tk. Tk. | 175.00 600.00 | each | = | Tk. Tk. | 43.75 300.00 |
| 2 | nos | @ | Tk. | 500.00 | per day | = | Tk. | 1,000.00 |
(iii) Skilled labour | 2 | nos | @ | Tk. | 390.00 | per day |
| Tk. | 780.00 |
(iv) Ordinary labour | 2 | nos | @ | Tk. | 320.00 | per day | = | Tk. | 640.00 |
(e) Washing of sand, scaffolding, curing, sundries, local carriage etc. |
|
|
| LS | = | Tk. | 192.00 | ||
|
|
|
|
|
| Sub - Total | = | Tk. | 3,392.75 |
|
|
|
|
| Profit | 10.00% | = | Tk. | 339.28 |
|
|
|
|
| Overhead | 3.50% | = | Tk. | 118.75 |
|
|
|
|
|
| Total | = | Tk. | 3,850.78 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 245.79 | |||
|
|
|
|
|
| Grand Total | = | Tk. | 4,096.57 |
|
|
|
|
|
| Rate per sft | = | Tk. | 40.97 |
|
|
|
|
|
| Rate per sqm | = | Tk. | 441.00 |
(i) For ground floor |
|
| Say, | Tk. | 441 .00 per sqm |
|
|
| |