|
|
| Say | Tk. | 567 | .00 per meter |
|
|
|
|
|
|
|
| |||||
Item No.- 23.6 |
|
|
|
|
|
|
|
|
|
Cast-in-situ Ferrocement wall Considering 100 sft of work |
|
|
|
|
|
|
|
|
|
1 Sand (F.M. 1.2) | 4.00 | cft | @ | Tk. | 14.00 | per cft | = | Tk. | 56.00 |
2 Sand (F.M. 2.2) | 10.00 | cft | @ | Tk. | 45.00 | per cft | = | Tk. | 450.00 |
3 Cement | 4.00 | bags | @ | Tk. | 415.00 | per bag | = | Tk. | 1,660.00 |
4 20 BWG galvanized wire mesh 2 mesh per | 210.00 | sft | @ | Tk. | 25.00 | per sft | = | Tk. | 5,250.00 |
25mm |
|
|
|
|
|
|
|
|
|
5 M.S. rod (fy = 400 Mpa) 8mm/6mm | 25.00 | kg | @ | Tk. | 60.50 | per kg | = | Tk. | 1,512.50 |
6 24 No. G.I. Wire | 1.00 | kg | @ | Tk. | 120.00 | per kg | = | Tk. | 120.00 |
7 Drill bit/Drill machine charge |
|
|
|
| L/S |
| = | Tk. | 100.00 |
8 Hire charge of Mixture machine including Oil | 0.12 | no | @ | Tk. | 2,004.00 | per day | = | Tk. | 240.48 |
& Operator |
|
|
|
|
|
|
|
|
|
9 Hire charge of Vibrator table including Oil & | 0.12 | no | @ | Tk. | 996.00 | per day | = | Tk. | 119.52 |
Operator |
|
|
|
|
|
|
|
|
|
10 Mason | 2.00 | nos | @ | Tk. | 500.00 | each | = | Tk. | 1,000.00 |
11 Rod binder | 1.00 | no | @ | Tk. | 500.00 | each | = | Tk. | 500.00 |
12 Helper to rod binder | 2.00 | nos | @ | Tk. | 390.00 | each | = | Tk. | 780.00 |
13 Skilled Labour | 2.00 | nos | @ | Tk. | 390.00 | each | = | Tk. | 780.00 |
14 Ordinary labour | 1.00 | no | @ | Tk. | 320.00 | each | = | Tk. | 320.00 |
15 Ordinary Labour for 7 days curing | 0.88 | no | @ | Tk. | 320.00 | each | = | Tk. | 280.00 |
16 Local Carriage, Sundries, T & P, water etc. | 0.20 | no | @ | Tk. | 320.00 | each | = | Tk. | 64.00 |
|
|
|
|
|
| Sub - Total | = | Tk. | 13,232.50 |
|
|
|
|
| Profit | 10.00% | = | Tk. | 1,323.25 |
|
|
|
|
| Overhead | 3.50% | = | Tk. | 463.14 |
|
|
|
|
|
| Total | = | Tk. | 15,018.89 |
| Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 958.65 | ||
|
|
|
|
|
| Grand Total | = | Tk. | 15,977.54 |
|
|
|
|
|
| Rate per sft | = | Tk. | 159.78 |
|
|
|
|
|
| Rate per sqm | = | Tk. | 1,719.23 |
|
|
| Say | Tk. | 1,719 .00 per sqm |
|
|
| |
|
|
|
|
|
|
|
|
|
|
Item No.- 23.7 |
|
|
|
|
|
|
|
|
|
Pre-cast Ferrocement wall panel |
|
|
|
|
|
|
|
|
|
Considering 100 sft of work 1 Sand (F.M. 1.2) | 2.34 | cft | @ | Tk. | 14.00 | per cft | = | Tk. | 32.76 |
2 Sand (F.M. 2.2) | 9.42 | cft | @ | Tk. | 45.00 | per cft | = | Tk. | 423.90 |
3 Cement | 4.40 | Bags | @ | Tk. | 415.00 | per bag | = | Tk. | 1,826.00 |
4 Polythene sheet | 50.00 | sft | @ | Tk. | 2.50 | per sft | = | Tk. | 125.00 |
5 8mm/6mm dia M.S. rod (fy = 400 Mpa) | 25.00 | kg | @ | Tk. | 60.50 | per kg | = | Tk. | 1,512.50 |
20 BWG galvanized wire mesh 2 mesh per 6 25mm | 200.00 | sft | @ | Tk. | 25.00 | per sft | = | Tk. | 5,000.00 |
7 Formwork/shuttering (steel) |
|
|
|
|
| L/S | = | Tk. | 200.00 |
8 Hire charge of Mixture machine including Oil | 0.25 | no |
| Tk. | 2,004.00 | per day |
| Tk. | 501.00 |
& Operator |
|
| @ |
|
|
| = |
|
|
9 Hire charge of Vibrator table including Oil & | 0.25 | no |
| Tk. | 996.00 | per day |
| Tk. | 249.00 |
Operator |
|
| @ |
|
|
| = |
|
|
10 Drill bit/Drill machine charge |
|
|
|
|
| L/S | = | Tk. | 100.00 |
11 Mason | 1.00 | no | @ | Tk. | 500.00 | each | = | Tk. | 500.00 |
12 Rod binder | 1.00 | no | @ | Tk. | 500.00 | each | = | Tk. | 500.00 |
13 Helper to rod binder | 1.00 | no | @ | Tk. | 390.00 | each | = | Tk. | 390.00 |
14 Skilled Labour | 1.00 | no | @ | Tk. | 390.00 | each | = | Tk. | 390.00 |
Local Carriage, Sundries, T &P, 15 Ordinary Labour for 7 days curing | 0.88 | no | @ | Tk. | 320.00 | each | = | Tk. | 280.00 |
16 (1/5 time of ordinary labour) | 0.20 | no | @ | Tk. | 320.00 | each | = | Tk. | 64.00 |
|
|
|
|
|
| Sub - Total | = | Tk. | 12,094.16 |
|
|
|
|
| Profit | 10.00% | = | Tk. | 1,209.42 |
|
|
|
|
| Overhead | 3.50% | = | Tk. | 423.30 |
|
|
|
|
|
| Total | = | Tk. | 13,726.88 |
| Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 876.18 | ||
|
|
|
|
|
| Grand Total | = | Tk. | 14,603.06 |