Item No.- 27.19.2.2 |
|
|
|
|
|
|
Supplying 75 mm dia(Class D) uPVC tube well pipe and blank pipe Considering 1 meter |
|
|
|
|
|
|
| Tk. | 308.33 | per meter | = | Tk. | 308.33 |
|
|
| LS | = | Tk. | 25.60 |
|
|
| Sub - Total | = | Tk. | 333.93 |
|
| Profit | 10.00% | = | Tk. | 33.39 |
|
| Overhead | 3.50% | = | Tk. | 11.69 |
|
|
| Total | = | Tk. | 379.01 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 24.19 |
|
|
| Grand Total | = | Tk. | 403.20 |
|
|
| Rate per rm | = | Tk. | 403.20 |
Say, | Tk. | 403 | .00 per meter |
|
|
|
|
|
|
|
|
|
|
Item No.- 27.19.2.3 |
|
|
|
|
|
|
Supplying 75 mm dia(Class E) uPVC tube well pipe and blank pipe |
|
|
|
|
|
|
Considering 1 meter
| Tk. | 701.22 | per meter | = | Tk. | 701.22 |
|
|
| LS | = | Tk. | 25.60 |
|
|
| Sub - Total | = | Tk. | 726.82 |
|
| Profit | 10.00% | = | Tk. | 72.68 |
|
| Overhead | 3.50% | = | Tk. | 25.44 |
|
|
| Total | = | Tk. | 824.94 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 52.66 |
|
|
| Grand Total | = | Tk. | 877.60 |
|
|
| Rate per rm | = | Tk. | 877.60 |
Say, | Tk. | 878 | .00 per meter |
|
|
|
|
|
|
|
|
|
|
Item No.- 27.19.3.1 |
|
|
|
|
|
|
Supplying 75 mm dia(Class C) uPVC strainer |
|
|
|
|
|
|
Considering 1 meter
| Tk. | 233.33 | per meter | = | Tk. | 233.33 |
| Tk. | 38.40 | per meter | = | Tk. | 38.40 |
|
|
| LS | = | Tk. | 25.60 |
|
|
| Sub - Total | = | Tk. | 297.33 |
|
| Profit | 10.00% | = | Tk. | 29.73 |
|
| Overhead | 3.50% | = | Tk. | 10.41 |
|
|
| Total | = | Tk. | 337.47 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 21.54 |
|
|
| Grand Total | = | Tk. | 359.01 |
|
|
| Rate per rm | = | Tk. | 359.01 |
Say, | Tk. | 359 | .00 per meter |
|
|
|
|
|
|
|
|
|
|
Item No.- 27.19.3.2 |
|
|
|
|
|
|
Supplying 75 mm dia(Class D) uPVC strainer |
|
|
|
|
|
|
Considering 1 meter
| Tk. | 308.33 | per meter | = | Tk. | 308.33 |
| Tk. | 38.40 | per meter | = | Tk. | 38.40 |
|
|
| LS | = | Tk. | 25.60 |
|
|
| Sub - Total | = | Tk. | 372.33 |
|
| Profit | 10.00% | = | Tk. | 37.23 |
|
| Overhead | 3.50% | = | Tk. | 13.03 |
|
|
| Total | = | Tk. | 422.59 |
Add VAT with adjustment factor |
| 1.06383 | 6.00% | = | Tk. | 26.97 |
|
|
| Grand Total | = | Tk. | 449.56 |
|
|
| Rate per rm | = | Tk. | 449.56 |
Say, | Tk. | 450 | .00 per meter |
|
|
|