Item No.- 01.2.1 |
Provide 3 sets as-built drawing using AutoCAD software in 23.38" x 16.54" (A-2) size standard drawing paper on completeion of works Considering per tender 23.38 16.54 2.69 sft
|
Sub - Total = Tk. 20,226.66 Profit 10.00% = Tk. 2,022.67 Overhead 3.50% = Tk. 707.93 |
Total = Tk. 22,957.26 Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,465.36 |
Grand Total = Tk. 24,422.62 |
Say, Tk. 24,423 .00 per tender |
|
Item No.- 01.2.2 |
Provide additional copy of as-built drawing using AutoCAD software in 23.38" x 16.54" (A-2) size standard drawing paper on completeion of works Considering 1 sheet 23.38" x 16.54" 23.38 16.54 2.685 sft
|
Sub - Total = Tk. 60.53 Profit 10.00% = Tk. 6.05 Overhead 3.50% = Tk. 2.12 |
Total = Tk. 68.70 Add VAT with adjustment factor 1.06383 6.00% = Tk. 4.39 |
Grand Total = Tk. 73.09 Rate per sft = Tk. 27.22 Rate per sqm = Tk. 293.00 |
Say, Tk. 293 .00 per sqm |
|
Item No.- 01.2.3 |
Provide coloured post-card size 10 nos progress photographs of works in 3 sets in each manth during entire contract period of works
|
Sub - Total = 1,170.00 Profit 10.00% = Tk. 117.00 Overhead 3.50% = Tk. 40.95 |
Total = Tk. 1,327.95 Add VAT with adjustment factor 1.06383 6.00% = Tk. 84.76 |
Grand Total = Tk. 1,412.71 |
Say, Tk. 1,413 .00 each month |
|
Item No.- 01.2.4 |
Prepare and Submission of implementation schedule using M.S. Project software (CPM Networking)
3 Printing of hard copy in 3 set 12.08 sft @ Tk. 18.00 per sft = Tk. 217.44 |
Sub - Total = Tk. 29,117.44 Profit 10.00% = Tk. 2,911.74 Overhead 3.50% = Tk. 1,019.11 |
Total = Tk. 33,048.29 |