Item No.- 01.2.1

Provide 3 sets as-built drawing using AutoCAD software in 23.38" x 16.54" (A-2) size standard drawing paper on completeion of works

Considering per tender 23.38 16.54 2.69 sft

  1. Survey, extg drg study by Engr/ Arch 7 day @ Tk. 1,800.00 per day = Tk. 12,600.00
  2. Inventory listing 3 day @ Tk. 800.00 per day = Tk. 2,400.00
  3. Autocad operator 3 day @ Tk. 800.00 per day = Tk. 2,400.00
  4. Checking by Arch/Engr 1 day @ Tk. 70,000.00 per month = Tk. 2,333.33
  5. Sundries Tk. 493.33 LS = Tk. 493.33

Sub - Total = Tk. 20,226.66

Profit 10.00% = Tk. 2,022.67

Overhead 3.50% = Tk. 707.93

Total = Tk. 22,957.26

Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,465.36

Grand Total = Tk. 24,422.62

Say, Tk. 24,423 .00 per tender

 

Item No.- 01.2.2

Provide additional copy of as-built drawing using AutoCAD software in 23.38" x 16.54" (A-2) size standard drawing paper on completeion of works

Considering 1 sheet 23.38" x 16.54" 23.38 16.54 2.685 sft

  1. Hardcopy 2.69 sft @ Tk. 18.00 per sft = Tk. 48.42
  2. Incidental, sundries etc. L.S = Tk. 12.11

Sub - Total = Tk. 60.53

Profit 10.00% = Tk. 6.05

Overhead 3.50% = Tk. 2.12

Total = Tk. 68.70

Add VAT with adjustment factor 1.06383 6.00% = Tk. 4.39

Grand Total = Tk. 73.09

Rate per sft = Tk. 27.22

Rate per sqm = Tk. 293.00

Say, Tk. 293 .00 per sqm

 

Item No.- 01.2.3

Provide coloured post-card size 10 nos progress photographs of works in 3 sets in each manth during entire contract period of works

  1. Cost for taking and editing photographs 1 day @ Tk. 1,100.00 per day = 1,100.00
  2. Printing & sundries 10 copies @ Tk. 7.00 per copy = 70.00

Sub - Total = 1,170.00

Profit 10.00% = Tk. 117.00

Overhead 3.50% = Tk. 40.95

Total = Tk. 1,327.95

Add VAT with adjustment factor 1.06383 6.00% = Tk. 84.76

Grand Total = Tk. 1,412.71

Say, Tk. 1,413 .00 each month

 

Item No.- 01.2.4

Prepare and Submission of implementation schedule using M.S. Project software (CPM Networking)

  1. Planning implementation schedule & micro 7 day @ Tk. 120,000.00 per month = Tk. 28,000.00
    networking using M.S. Project software or in equivalent software
  2. Developing hard-copy of networking 0.5 day @ Tk. 1,800.00 per day = Tk. 900.00

3 Printing of hard copy in 3 set 12.08 sft @ Tk. 18.00 per sft = Tk. 217.44

Sub - Total = Tk. 29,117.44

Profit 10.00% = Tk. 2,911.74

Overhead 3.50% = Tk. 1,019.11

Total = Tk. 33,048.29